Benchmarks for Investment Grade Power Projects
Author: Goldsmith, Deborah; Brooks, Andrew; Chew, William; Moulton ,
Curtis
There are no set guidelines for investment grade power project financings.
Each individual financing is approached in light of the particular credit
profiles of participants, the different structural and contractual arrangements,
and the unique characteristics of each regulatory and market environment.
However, S&P has identified some benchmarks that are important in establishing
investment grade strength for each of the more crucial rating factors.
The weighting of each of these rating factors will depend on each project's
unique characteristics.
1. Output sales contract.
Capacity payments should cover debt service and other fixed project costs.
Availability minimum requirements should not raise material risk to project
revenue given the technology.
- Energy: Load factor
guarantees if certain availability factors are met, and if payment is
divided between a variable and fixed energy rate component, with the
fixed component based on availability, not generation. The fixed energy
rate should be able o cover minimum inventory charges, as well as other
fixed charges, like minimum fuel takes.
- Dispatch: If under
utility control, the expected mode of dispatch should be economic. This
is not a concern if project costs economics are sound compared to the
utility's embedded cost. Ideal project arrangements would have a guarantee
of a minimum number of hours for which a project can be dispatched.
- No "regulatory
out" clause, unless the underrecovery of the buyer is deferred until
the end of the debt term. Exceptions may be made only where S&P is extremely
comfortable with the future rate-making environment.
- Thermal sales:
The host for a qualifying facility project should be investment grade
status. Exceptions may be considered, depending on circumstances. The
plant should be an integral part of the host's operations.
2. Power costs
Power costs should not only be below avoided cost of the buying utility,
but should also be reasonable when compared to the regional embedded cost
of power. Avoided cost should not be at risk of being unusually high prospectively
due to limited fuel protection or known changes in market supply demand
conditions in the intermediate term (such as known large capacity additions
in the region that could create surplus supply conditions over the intermediate
term). The project should also be economically priced for the seller,
so that the seller is not at risk of significant margin squeeze in the
event of a potential change in external conditions.
3. The fuel source should be adequate
The terms of the fuel contract should at least be the same as the debt
term. No prospective risk should be evident that could interrupt supply;
i.e., transportation capacity should be adequate and contracted for the
same period as fuel supply contracts. Suppliers should be financially
sound. Pricing should be fully hedged. The index used fir supply and sales
output energy pricing should be the same and readjustments to indexes
for each contact should be at the same time. Transportation costs should
not run the risk of deviating significantly from assumed transportation
pricing in the energy pricing. All supply should be domestic. Exceptions
to this rule can be made with Canadian suppliers, depending on how the
fuel supply agreements are structured and on how pricing compares to average
world prices.
4. Structure
The project should be structured as a single-purpose entity with no allowance
for additional debt. At least 15% equity is required by ownership participants.
This will vary depending upon technology. Reserves should be established
to at least cover six months' debt service. If the technology is complex,
operating and maintenance (O&M) reserves should be established for at
least six months. Funding of reserves should be within five years, with
no partnership withdrawals until reserves are fully funded. Cross default
provisions should be tied to all integral contracts. Insurance provisions
should exist to include adequate coverage for property damage and business
interruption.
5. Technology
- The operator's
experience record should be sound. If there is a third party O&M contractor,
proper incentives and penalties should be written into the agreement,
particularly if the contract calls for a straight pass-through of costs.
- The operator should
have extensive experience and a solid performance record with the technology
being used.
- Availability requirements
in output sales agreements should not be unreasonable for the technology
given expected scheduled and unscheduled outages.
- Warranties for
key operating equipment should exist for at least the first year of
operation.
- The contracting
engineer should guarantee performance standards at operation. If initial
testing fails below required capacity utilization levels, liquidated
damages should be set at levels that would pay down debt in an amount
that would still allow for the same required coverage levels.
- A project feasibility
review must be made by an independent engineer experienced in the technology
being employed.
6. The purchaser should
be at least investment grade.
How far the project's rating would be below this credit rating would depend
upon the economics. Sound economics and adequate transmission could allow
the project's debt to be rated close to, if not equal to, the buying utility's
senior debt rating. In very rare cases, if the power could easily be sold
elsewhere, the credit rating could be placed above the utility's senior
debt rating.
7. Financial projections
The key ratio to be used in analysis of project economics is a fixed charge
ratio calculated as follows:
This ratio benchmark will vary depending upon fuel type and technology.
Adequate coverage ratios would be about 1.5 times for the first three
years of operation, with the average over the life at about 1.7x. However,
this is just a starting minimum, and the ranges would vary depending upon
other project risk characteristics.
The quality of the financial projections is just as important and would
depend on an analysis of underlying assumptions. Sensitivity analysis
should incorporate an analysis of the potential change in a combination
of factors. The more sensitive cash flow is to assumptions that have a
high probability of variability, the lower the quality of the projections.
CREDIT BENCHMARKS
To achieve investment-grade or near-investment-grade ratings, projects
will need compelling credit strength in each of the key analytical areas.
For most projects, this will include:
- Very low-risk
technology and low site risk: In most cases, this can be established
by ample record of comparable projects on similar sites being completed
with few or no cost overruns and construction delays.
- Conservative construction
schedule. Projects with longer construction schedules will only be able
to achieve investment-grade or near-investment-grade ratings when vendors
and contractors are able to demonstrate overwhelming capacity to manage
the accompanying risk. Construction budgets also should include schedule
cushions and reserves to cover worst-case delays and cost overruns.
- Strong turnkey
construction contracts. The contract should shift substantially all
construction risk to contractors and vendors.
- Adequate capacity
to perform on contract obligations. This will be demonstrated by a rating
or financial guarantee in the form of an LOC or surety bond providing
for payment of contract damages and penalties in sufficient time to
maintain cash flow required for debt service.
- Contractors and
vendors should be able to show extensive experience building comparable
projects at or ahead of budget and schedule. Power project construction
also should be a major part of the long-term business strategy of key
contractors and equipment suppliers.
- Strong third-party
trustee structure for management of construction funds. The trustee
should be experienced in administration and management of power project
construction, preferably as a lender, and should retain an experienced
engineer independent of any other interest on the project.
- The process of
obtaining permits should be as free as possible from the potential for
significant changes in law or regulation. This is best accomplished
where project and site have support from both surrounding community
and all other affected parties, including output purchasers and environmental
interests. In addition, acceptance standards should incorporate the
emission levels approved under the project's environmental permits.
|

Issues
Banks
Corporates
Securities
Insurance
Financial
Holding Company
Bond Funds
Equity
Funds
Public Finance
RMBS
REBS
Bank Securities |